Fallon Paiute-Shoshone Tribe et al v. U.S. Department of the Interior et al
Case Number:
3:21-cv-00512
Court:
Nature of Suit:
Other Statutes: Administrative Procedures Act/Review or Appeal of Agency Decision
Judge:
Firms
Companies
Government Agencies
Sectors & Industries:
-
July 06, 2023
BLM To Revisit Enviro. Assessment For Geothermal Project
The U.S. Department of the Interior notified a Nevada federal judge that it plans to revisit an environmental assessment approving a geothermal project in the state, following its Endangered Species Act consultation efforts and the unveiling of new information.
-
November 10, 2022
Enviros, Tribe Tell Court Not To Wait On Geothermal Dispute
The Center for Biological Diversity and the Fallon Paiute-Shoshone Tribe told a Nevada federal judge their lawsuit challenging the government's approval of a geothermal project in the state should not be put on hold for the government to consider a new, scaled-back project proposal.
-
September 19, 2022
Judge Told Nev. Power Plant Threatens Endangered Toad
The federal government's approval of a Nevada geothermal power plant must be wiped out because regulators clearly ignored the project's risks to the endangered Dixie Valley toad, a Native American tribe and an environmental group told a Nevada federal judge.
-
August 01, 2022
9th Circuit Won't Block Nevada Geothermal Plant
The Ninth Circuit refused Monday to bar construction on a Nevada geothermal power plant after finding the Center for Biological Diversity and the Fallon Paiute-Shoshone Tribe hadn't shown their challenge of federal approvals for the project is likely destined for success.
-
January 27, 2022
Geothermal Co. Asks 9th Circ. To Let Plant Project Go Forward
A Nevada geothermal plant developer has told the Ninth Circuit that it should lift a lower court judge's restraining order keeping it from starting construction, arguing that doing so is necessary to avoid major disruptions to its timeline and ability to meet key deadlines.
-
January 18, 2022
Judge Sticks With Construction Halt On Power Plant
A Nevada federal judge is standing by an injunction temporarily stopping construction on a planned geothermal power plant, despite concerns raised by the developer that the delay risks costing the company more than $30 million.
-
January 12, 2022
Power Co. Pans Construction Halt On Geothermal Power Plant
The developer of a Nevada geothermal power plant says a 90-day preliminary injunction on construction would make it "virtually impossible" to complete the project by a key contractual deadline and would cost the company $30 million.
-
January 04, 2022
Judge Temporarily Blocks 2 Geothermal Power Plants In Nev.
A developer must wait at least 90 days before breaking ground on two planned Nevada geothermal power plants after a federal judge was swayed Tuesday by arguments the project could ruin sacred tribal grounds and devastate a rare toad's population.